JOIN THE TEAM

PROJECTS

UPM II - Chemical Recovery Island

Location: Paso de los Toros, Uruguay
Year: 2020 - 2020
Construction of reinforced concrete foundations for the plant's recovery boilers. More than 7,200 m3 poured continuously with temperature control and high performance concretes. In total, the work required 28,000 m3 of concrete.

MORE PROJECTS