UPM II - Turbine Building Piping

Location: Paso de los Toros, Uruguay
Year: 2021 - 2023
Within the turbine building, 623 tons of piping were installed with a total of 96,300 welded inches, reaching a length of 13 km of piping. Equipment was also installed for a total weight of 223 tons, including compressors, pumps, dryers, filters, silencers, sampling stations and hydraulic units, among others.